Date: Wed, 3 Mar 2010 16:30:37 -0800
From: Andrew Sharp <andy.sharp@lsi.com>
To: Brian Stark <brian.stark@lsi.com>
Subject: RFC: tuxstor schedule/plan beta
Message-ID: <20100303163037.494b53a6@ripper.onstor.net>
Organization: LSI
X-Mailer: Sylpheed-Claws 2.6.0 (GTK+ 2.8.20; x86_64-pc-linux-gnu)
Mime-Version: 1.0
Content-Type: text/plain; charset=US-ASCII
Content-Transfer-Encoding: 7bit

I've put together a beta schedule/plan based on what we talked about
yesterday.

http://ripper.onstor.net/~andys/company/eng/tuxstor/tuxstor-p1-sched-beta.pdf

The one on the wiki can be found at:

http://wiki.onstor.net/wiki/Tuxstor_Roadmap_-_Platform_Group



Notes:

We need to pull the trigger on some of these work assignments if we are
to make good on this new schedule.  How do you want to do this wrt to
Jobi's people?  Can we start Usha on the Qlogic interrupt handler now,
and if things get ugly, she can just be reassigned?  I'd really like
for the training of Usha to begin.  The interrupt handler is not
critical.

I have put together some task lists on the beta schedule to deal a
death blow to RMC and the bugs that stream from it.  I have not
assigned them to anyone, so they don't have schedule bars.  I was
thinking maybe Terrence?  Take a look at the items in those two new
task lists and let me know what you think.

Cheers,

a